If the best operating level of a piece of equipment is at a rate of 400 units per hour and the actual output during an hour is 300 units, which of the following is the capacity cushion?
A) 25 percent
B) 100 units per hour
C) 75 percent
D) 125 percent
E) 133 percent
Correct Answer:
Verified
Q50: Which of the following is not a
Q51: What is an important difference between capacity
Q52: Specialized workers require broader training than flexible
Q53: Service capacity planning is performed almost identically
Q54: The capacity focus concept can be put
Q56: If the actual output of a piece
Q57: The volatility of demand on a service
Q58: With decision trees, squares represent chance events
Q59: Capacity planning involving acquisition or disposal of
Q60: Capacity planning that involves hiring, layoffs, some
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents