A project has four activities: A, B, C, and D. The amount spent on each activity to date is $22K, $14K, $12K, and $28K respectively. The planned percentages complete for the current date are 90%, 80%, 70%, and 20% respectively. The actual percentages complete for the current date are 100%, 90%, 75%, and 10% respectively. The actual cost of the work performed to date is $40K. What is the BCWS for Activity D?
A) $0 − $5K
B) $5.01K − $10K
C) $10.01K − $15K
D) $15.01K − $20K
E) Over $20K
Correct Answer:
Verified
Q80: Here are the data for a time-cost
Q81: This is usually a written description of
Q82: Pieces of work within a project that
Q83: A project has four activities: A, B,
Q84: Which of the following is not an
Q86: Which of the following is not a
Q87: A project has four activities: A, B,
Q88: A specific event in a project is:
A)
Q89: Which of the following is not a
Q90: Which of the following is not a
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents