Table J.1 The Framing Department Has Six Jobs Waiting to Be Processed

Question 22

Multiple Choice
Table J.1
The framing department has six jobs waiting to be processed. It is now time zero. Times are expressed in terms of days.
 
-Using the information in Table J.1 and the EDD rule, what is the average early time?
A) 0 days 
B) greater than 0 but less than 1.5 days 
C) greater than 2.5 but less than 2.5 days 
D) greater than 2.5 days

Table J.1
The framing department has six jobs waiting to be processed. It is now time zero. Times are expressed in terms of days.
Table J.1 The framing department has six jobs waiting to be processed. It is now time zero. Times are expressed in terms of days.    -Using the information in Table J.1 and the EDD rule, what is the average early time? A)  0 days B)  greater than 0 but less than 1.5 days C)  greater than 2.5 but less than 2.5 days D)  greater than 2.5 days
-Using the information in Table J.1 and the EDD rule, what is the average early time?


A) 0 days
B) greater than 0 but less than 1.5 days
C) greater than 2.5 but less than 2.5 days
D) greater than 2.5 days

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents