Larry's Wickets, Inc. is producing two types of products: A and B. Both are produced at the same machining operation. Because of demand uncertainties, the operations manager obtained three demand forecasts (pessimistic, expected, and optimistic). The demand forecasts, batch sizes (units/batch), processing times (hr/unit), and setup times (hr/batch) follow.
The machines operate on two 8-hour shifts, 5 days per week, and 50 weeks per year. The manager wants to maintain a 20 percent capacity cushion.
a. What is the minimum number of hours required of the machining equipment for the next year?
b. How many hours of capacity can the company expect from each machine?
c. What is the minimum number of machines needed (assuming no reliance on short-term options)?
d. What is the maximum number of machines needed (assuming no reliance on short-term options)?
Correct Answer:
Verified
a. 81,800 hours
b....
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q100: Scenario 4.6
Burdell Labs is a diagnostic laboratory
Q101: Burdell Labs is a diagnostic laboratory that
Q102: Extremely complex service capacity problems for which
Q103: What information would managers use to choose
Q104: Figure 4.1 Q106: The Union Manufacturing Company is producing two Q107: What is a waiting line model, and
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents