Use the process flow diagram to determine which of these events has the greatest net benefit.
A) reducing the flow time at Station A from 8 to 7 minutes
B) increasing the capacity at Station B to 8 units per hour
C) increasing the capacity at Station C to 7 units per hour
D) reducing the flow time at Station D from 9 to 8 minutes
Correct Answer:
Verified
Q3: The focus for a process improvement exercise
Q4: _ is the maximum rate of output
Q5: The fifth step in Theory of Constraints
Q6: The Theory of Constraints method is also
Q7: The second step in Theory of Constraints
Q9: A bottleneck is an operation that has
Q10: Consider consecutive processes A-B-C, where process A
Q11: Lanny discovers that the bottleneck is the
Q12: The third step in Theory of Constraints
Q13: Use the process flow diagram to determine
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents