Solved

Table 5.4 The Superior Management Company Assembles Muffalettas in the Big Easy

Question 114

Multiple Choice
Table 5.4
The Superior Management Company assembles muffalettas in The Big Easy. The steps to making a world class sandwich and the time required (in seconds) for each step are shown in the table.
 
-Customers demand muffalettas at the rate of 20 sandwiches per hour. Use the information in Table 5.4 to determine the maximum efficiency you can achieve balancing this line with an output rate that meets demand.
A) 84% 
B) 100% 
C) 76% 
D) 92%

Table 5.4
The Superior Management Company assembles muffalettas in The Big Easy. The steps to making a world class sandwich and the time required (in seconds) for each step are shown in the table.
Table 5.4 The Superior Management Company assembles muffalettas in The Big Easy. The steps to making a world class sandwich and the time required (in seconds)  for each step are shown in the table.    -Customers demand muffalettas at the rate of 20 sandwiches per hour. Use the information in Table 5.4 to determine the maximum efficiency you can achieve balancing this line with an output rate that meets demand. A)  84% B)  100% C)  76% D)  92%
-Customers demand muffalettas at the rate of 20 sandwiches per hour. Use the information in Table 5.4 to determine the maximum efficiency you can achieve balancing this line with an output rate that meets demand.


A) 84%
B) 100%
C) 76%
D) 92%

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents