Solved

An Item Sells at a Rate of 600 Units Per

Question 97

Essay
An item sells at a rate of 600 units per day. If a plant works two shifts per day (480 minutes each shift), what takt time is required for the plant to meet this demand?

An item sells at a rate of 600 units per day. If a plant works two shifts per day (480 minutes each shift), what takt time is required for the plant to meet this demand?

Correct Answer:

verifed

Verified

480 minutes per shift × 2 shif...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents