Degan's Salad Dressings Uses a Kanban System

Question 129

Essay
Degan's Salad Dressings uses a Kanban system. The daily demand for corrugated boxes used in packaging its dressings is 300 boxes. The average waiting time for a container of boxes is 0.25 day. The processing time for a container of boxes is 0.1 day, and a container holds 10 boxes. If Burdell wishes to use a 10% policy variable, how many containers are needed?

Degan's Salad Dressings uses a Kanban system. The daily demand for corrugated boxes used in packaging its dressings is 300 boxes. The average waiting time for a container of boxes is 0.25 day. The processing time for a container of boxes is 0.1 day, and a container holds 10 boxes. If Burdell wishes to use a 10% policy variable, how many containers are needed?

Correct Answer:

verifed

Verified

k = blured image = blured image = ...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents