The final assembly schedule in a lean system:
A) should be developed for each product independent of the process requirements for the other products.
B) strives to create a uniform flow at the work centers in the plant.
C) avoids the use of small lot sizes because they create many production orders and cause confusion.
D) allows daily changes in demand levels, regardless of size, to be incorporated immediately into the work center schedules.
Correct Answer:
Verified
Q156: _ is a qualitative lean tool for
Q157: Choose a simple, common process and create
Q158: Scenario 6.1
El Gran Raton, the producers of
Q159: Which of the following is a process
Q160: Which one of the following is an
Q161: What are the organizational issues companies must
Q162: If the inventory advantages of a lean
Q163: What is schedule stability and why is
Q164: Describe the process considerations organizations must evaluate
Q166: Transforming a current process design to one
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents