A project has three paths. A-B-C has a length of 25 days. A-D-C has a length of 15 days. Finally, A-E-C has a length of 20 days. Which one of the following statements is True?
A) A-D-C is the critical path.
B) A-B-C has the most slack.
C) The expected duration of this project is 25 days.
D) The expected duration of this project is 25 + 15 + 20 = 60 days.
Correct Answer:
Verified
Q29: A Gantt chart is a project schedule
Q30: Figure 7.2 Q31: The _ is the sequence of activities Q32: The earliest start time for an activity Q33: The earliest start time is never the Q35: Activity slack is defined as: Q36: Assume that activity G has the following Q37: Figure to accompany Table 7.1 Q38: Figure to accompany Table 7.1 Q39: Figure 7.1
![]()