If the sum of the variances on the critical path (and all other network paths) is equal to zero, what is the probability that the project will be completed by its earliest expected completion date?

If the sum of the variances on the critical path (and all other network paths) is equal to zero, what is the probability that the project will be completed by its earliest expected completion date?


A) 50 percent
B) 95 percent
C) 100 percent
D) It cannot be determined.