Solved

Table 10.10 a Work Center Has the Following Six Jobs Waiting to Waiting

Question 122

Multiple Choice
Table 10.10
A work center has the following six jobs waiting to be processed (all times are shown in days):
 
-Use the information in Table 10.10. What is the average flow time (in days) using the FCFS rule?
A) fewer than or equal to 10 days 
B) greater than 10 days but fewer than or equal to 20 days 
C) greater than 20 days but fewer than or equal to 30 days 
D) greater than 30 days

Table 10.10
A work center has the following six jobs waiting to be processed (all times are shown in days) :
Table 10.10 A work center has the following six jobs waiting to be processed (all times are shown in days) :    -Use the information in Table 10.10. What is the average flow time (in days)  using the FCFS rule? A)  fewer than or equal to 10 days B)  greater than 10 days but fewer than or equal to 20 days C)  greater than 20 days but fewer than or equal to 30 days D)  greater than 30 days
-Use the information in Table 10.10. What is the average flow time (in days) using the FCFS rule?


A) fewer than or equal to 10 days
B) greater than 10 days but fewer than or equal to 20 days
C) greater than 20 days but fewer than or equal to 30 days
D) greater than 30 days

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents