Essay

Use the information in the preceding table and sequence the six jobs using first come, first served (FCFS) and earliest due date (EDD). Calculate the average flow time and average past due. It is now time zero.
Correct Answer:
Verified
Average Flow Time = 166 ÷ 6 ...