A defense contractor has just started producing turbines for a new government contract. The first turbine took 7000 hours to produce. If the learning curve is 90%, how long will it take to produce the 10th turbine? (Use at least three decimals in the exponent if you use the formula approach.)
A) less than 4800 hours
B) from 4800 to 4900 hours
C) from 4900 to 5000 hours
D) from 5000 to 5100 hours
E) over 5100 hours
Correct Answer:
Verified
Q58: In the formula to compute the time
Q59: The first product took 10 hours to
Q60: If it took 1000 hours to produce
Q61: Suppose that there are two products with
Q62: The first unit of a product took
Q64: In the Learning-Curve Coefficients table for 80
Q65: To use the table of learning-curve coefficients,
Q66: A defense contractor has just started producing
Q67: The first unit of a product took
Q68: In the formula approach to learning curve
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents