A contractor builds large ships for the Department of Defense. A recent contract called for 12 amphibious landing platforms. It was originally estimated that the first of these would cost $1 billion and that 80 percent learning would be appropriate. In fact, the first ship cost $1.6 billion and the second $1.12 billion. What is the revised learning curve? What will be the total cost of the 12 ships? Is it higher or lower than the original estimate? If the defense department cuts the contract from 12 ships to 9, what happens to the average cost per ship?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q77: A company negotiates a price for two
Q78: The first unit of a product took
Q79: A manager is trying to estimate the
Q80: The _ is the simplest approach to
Q81: A company is preparing a bid on
Q83: A product was priced assuming a 75%
Q84: Sally suspects strongly that there is a
Q85: The fourth unit of production took 80
Q86: A small manufacturer builds wooden pleasure boats
Q87: You are about to undertake the manufacture
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents