Lead time for cakes is 2 days with daily demand of 4 cakes and a safety stock of 1/2 day. Each container (kanban) holds 2 cakes. What is the correct number of kanbans?
A) 4
B) 1
C) 5
D) 10
E) 25
Correct Answer: