A product has annual demand of 1,000,000 units. The plant manager wants production to follow a two-hour cycle. Based on the following data, what setup time will enable the desired production cycle? d = 4000 units per day (250 days per year) , p = 8000 units per day, H = $60 per unit per year, Q = 1000 (demand for two hours) , and the hourly labor rate is $30.
A) 30 minutes
B) 0.5 minutes
C) 15 minutes
D) 2.85 minutes
E) 5.7 minutes
Correct Answer:
Verified
Q94: Which of the following is FALSE regarding
Q95: Identify the layout tactics appropriate for a
Q96: What are the goals of JIT partnerships?
Q97: What are the five reasons given by
Q98: Identify some of the signals that kanban
Q100: Describe level schedules. What purpose do they
Q101: Which of the following is NOT characteristic
Q102: Which of the following is an illustration
Q103: Japanese call the practice of stopping production
Q104: A bakery uses 5 kanban containers that
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents