Five welding jobs are waiting to be processed. Their processing times and due dates are given below. Using the critical ratio dispatching rule, in which order should the jobs be processed? All dates are specified as days from today.
A) B, D, A, E, C
B) C, D, A, B, E
C) C, E, A, D, B
D) E, B, A, D, C
E) B, D, A, C, E
Correct Answer:
Verified
Q57: Earliest due date is a shop floor
Q58: The president of a consulting firm wants
Q59: What is input-output control?
Q60: Three jobs are to be assigned to
Q61: Five jobs are waiting for processing through
Q63: EDD stands for what?
A) earliest due date
B)
Q64: Average completion time for a schedule sequence
Q65: Eight jobs have been sequenced at a
Q66: What does the use of the shortest
Q67: Sequencing (or dispatching):
A) assigns dates to specific
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents