Which of the following best describes a gross material requirements plan?
A) a schedule that shows total demand for an item, and when it must be ordered from a supplier or when production must be started
B) an intermediate range plan for the scheduling of families of products
C) a chart illustrating whether capacity has been exceeded
D) a table that corrects scheduled quantities for inventory on hand
E) a schedule showing which products are to be manufactured and in what quantities
Correct Answer:
Verified
Q51: Explain the difference between a gross requirements
Q52: Each R requires 3 of component S
Q53: In MRP, the number of units projected
Q54: It is week 1 and there are
Q55: Each X requires 2 of component Y
Q57: Construct a product structure tree for a
Q58: An order for 100 units of Product
Q59: If 100 units of Q are needed
Q60: Consider the following product structure.
Q61: Product A is made from 2 Bs
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents