If a load report (resource requirements profile) shows a work center scheduled beyond capacity:
A) the company must add capacity by enlarging the facility.
B) the company must add capacity by such tactics as overtime and subcontracting.
C) the work center's load may be smoothed by such tactics as operations splitting or lot splitting.
D) the aggregate plan must be revised.
E) the Wagner-Whitin algorithm should be used to rebalance the load.
Correct Answer:
Verified
Q106: MRP II is accurately described as:
A) MRP
Q107: Which of the following statements is TRUE
Q108: _ is a system that allows, with
Q109: Consider the following requirements for a certain
Q110: Consider the bill of material for Product
Q112: A very simple product (A) consists of
Q113: What do we mean by closed-loop MRP?
Q114: Jacquie Welkener, operations manager for ABC Technologies,
Q115: Why will the POQ almost always outperform
Q116: Smoothing a resource requirements profile to stay
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents