Audrey Ross, operations manager for BCD Technologies, must schedule work for the next five days. Each unit takes 20 minutes to process. Available capacity is 8 hours per day. The production order quantities are 18, 28, 38, 16, and 20 for Monday through Friday, respectively. What should be the plan for Wednesday?
A) Move 2 units to Monday, 8 units to Thursday, and 4 units to Friday.
B) Move 8 units to Monday, 8 units to Thursday.
C) Move 4 units to Tuesday, and 10 units to Thursday.
D) Move 2 units to Tuesday, 6 units to Thursday, and 6 units to Friday.
E) Move 8 units to Thursday, and 4 units to Friday.
Correct Answer:
Verified
Q112: A very simple product (A) consists of
Q113: What do we mean by closed-loop MRP?
Q114: Jacquie Welkener, operations manager for ABC Technologies,
Q115: Why will the POQ almost always outperform
Q116: Smoothing a resource requirements profile to stay
Q118: A(n) _ provides feedback to the capacity
Q119: Clancy's Motors has the following demand to
Q120: Operations splitting sends pieces to the next
Q121: Blockchain software replaces paper-based transaction records with
Q122: Distribution resource planning (DRP) is:
A) a transportation
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents