Cyclone Appliances has developed a new European-style convection oven that will be made on an assembly line. The schedule requires 100 ovens in an 8-hour day. The assembly includes seven tasks. The table below indicates the performance time and the sequence requirements for each task.
(a) What is the cycle time for this assembly operation?
(b) What is the theoretical minimum number of workstations?
(c) Draw the precedence diagram.
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q298: A production line is to be designed
Q299: Which of the following is one of
Q300: A production line is to be designed
Q301: Explain what the purpose of assembly-line balancing
Q302: A company is designing a product layout
Q304: An assembly line has been designed to
Q305: An electronics manufacturer makes remote control devices
Q306: A facility is trying to set up
Q307: Assembly line balancing has just been used
Q308: _ is the maximum time that the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents