Which of these statements regarding time-cost tradeoffs in CPM networks is TRUE?
A) Crashing is possible even if there are multiple critical paths.
B) Crashing a project often reduces the length of long-duration, but noncritical, activities.
C) Activities not on the critical path can never be on the critical path, even after crashing.
D) Crashing shortens the project duration by assigning more resources to one or more of the noncritical tasks.
E) The crash time always exceeds the normal time.
Correct Answer:
Verified
Q101: A project whose critical path has an
Q102: A project manager determined that the project
Q103: A network consists of the following list.
Q104: Two activities on the same critical path
Q105: The _ distribution is appropriate for calculating
Q107: How is the expected completion time of
Q108: A project whose critical path has an
Q109: A project manager is interested in crashing
Q110: PERT calculations typically include the duration variance
Q111: In PERT, project variance is computed by
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents