Solved

A Swimming Pool Company Has 100,000 Labor Hours Available Per

Question 131

Essay

A swimming pool company has 100,000 labor hours available per summer and with a labor productivity of 5 pools per 4,000 hours.
(a) How many pools can the company install this summer?
(b) Suppose the multifactor productivity was one pool per $25,000. How much should the company expect to spend this summer constructing the pools?

Correct Answer:

verifed

Verified

(a) 100,000 hours × ...