Solved

Consider a Five-Year Project That Costs $20,000 Today, Which Is

Question 77

Multiple Choice

Consider a five-year project that costs $20,000 today, which is expected to generate $6,000 at the end of the second year and then the cash flows will increase by $1,000 per year for each of the remaining years.The cost of capital is 8%.What are the NPV and IRR for this project?


A) NPV = $1,083.24; IRR = 8.96%
B) NPV = $2,706.35; IRR = 11.93%
C) NPV = $3,824.56; IRR = 14.87%
D) NPV = $4,522.85: IRR = 17.09%

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents