Juliana Estimates That There's a 50% Probability That the Construction

Question 129

Multiple Choice

Juliana estimates that there's a 50% probability that the construction of her company's new data storage facility will be completed within the next month.However, she believes that it is 30% likely that the construction will take two months, and 20% likely it will take a full three months.She also believes that if the construction is completed within one month, there is a 65% likelihood that she can have the facility fully staffed and operational by summer.If the construction takes two months, the chances of meeting the summer deadline drops to 40%; and if the construction takes three months, there is only a 10% probability meeting the summer deadline.How likely is it that Juliana will not meet the summer deadline?


A) .200
B) .346
C) .685
D) .282
E) .535

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents