Which statement is true regarding a liquidated damages clause?
A) A provision for liquidated damages is illegal.
B) A provision for liquidated damages is void because of public policy.
C) A provision for liquidated damages is voidable because of public policy.
D) A provision for liquidated damages is enforceable so long as it is not punitive in nature.
E) A provision for liquidated damages will be enforced regardless of whether it is punitive in nature.
Correct Answer:
Verified
Q33: If the parties do not agree to
Q34: Fred's Fireplaces enters into a contract with
Q35: Patty, a buyer, breaches her contract with
Q36: Fred's Fireplaces enters into a contract with
Q37: When may a lessor seek incidental damages
Q39: A seller who sells goods to another
Q40: What was the result in the text
Q41: _ refers to the right of a
Q42: Miguel, a buyer becomes insolvent and has
Q43: When a lessee in possession of the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents