Suppose that as a result of a public project evaluation the following information was obtained:- PW of the project's capital costs = $9 million- PW of the project's operating costs = $5 million- PW of the project's benefits = $20 millionWhat is the BCRM for this project?
A) 0.42
B) 0.67
C) 1.07
D) 1.67
E) 2.20