Cost slope can be determined by dividing the
A) run by the rise.
B) rise by the run.
C) crash cost by the normal cost.
D) normal cost by the crash cost.
E) indirect cost by direct cost.
Correct Answer:
Verified
Q25: Before crashing, direct costs for an activity
Q26: One of the advantages of using a
Q27: Which of the following is NOT considered
Q28: The simplest way to reduce cost on
Q29: As a project is crashed and project
Q31: Design flaws, equipment breakdown and adverse weather
Q32: The accuracy of crash times and costs
Q33: For most projects, the estimation of a
Q34: An activity's crash cost includes _ costs.
A)
Q35: Making the decision to crash is the