When reducing project duration, the crash cost per unit has to be calculated and the maximum units each activity can be reduced must be known. After this, the critical path must be identified. What is the next step?
A) Find the activity with the lowest crash cost
B) Calculate the optimum cost-time point
C) Calculate the crash point
D) Calculate indirect cost per time unit
E) Find the activity with the steepest cost slope
Correct Answer:
Verified
Q51: Which of the following is NOT a
Q52: Reducing project duration
A) involves crashing all activities
Q53: In selecting the best activity to crash
Q54: One way of reducing project costs is
Q55: All of the following are disadvantages of
Q57: According to Brooks' Law, adding more people
Q58: An activity's normal time and cost are
Q59: Helen has just learned that she needs
Q60: The less steep the cost slope of
Q61: The direct cost for completing an activity
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents