Consider the Following Table of Activities That Describes a Project

Question 91

Multiple Choice

Consider the following table of activities that describes a project network. Without causing the critical path to become noncritical or otherwise wasting money, by how many days max could you crash this project? Assume you can crash only one activity at a time and that crashing is necessary regardless of cost. You do not want to crash the critical path(s) beyond the point where it (they) is no longer critical as this will not reduce project duration.


A) From 60 days to 50 days
B) From 60 days to 40 days
C) From 60 days to 30 days
D) From 60 days to 20 days
E) From 60 days to 10 days

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents