A project leader has realized that two activities in the project cannot be done at the same time because not enough resources are available. Activity 3 is critical and has a duration of 5 days. Activity 4 has 2 days of slack and a duration of 2 days. How will the project leader decide which activity should be scheduled first?
A) The activity with the smallest duration
B) The activity with the least slack
C) The activity with the most slack
D) The activity with the lowest identification number
E) The activity with the highest cost
Correct Answer:
Verified
Q51: These are all guidelines a project manager
Q52: Which of the following is NOT one
Q53: In a resource-constrained project, which of the
Q54: In a resource-constrained project the third priority
Q55: A project scheduler is working on a
Q57: A project scheduler is trying to reallocate
Q58: All of the following are benefits of
Q59: In a resource-constrained project, the first, or
Q60: Project budgets are developed by time-phasing which
Q61: When developing project networks, which of the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents