A project manager has two engineers assigned to the project and does not have access to more even if the result means extending the completion date on the project. The project manager is managing a(n) ________.
A) time-constrained project
B) people-constrained project
C) engineer-constrained project
D) resource-constrained project
E) human-constrained project
Correct Answer:
Verified
Q71: A shortage of software developers to create
Q72: When scheduling activities in a resource-constrained project,
Q73: In order that the new product is
Q74: If three copiers are needed to produce
Q75: When deciding which staff to team-up to
Q77: Which of the following questions does a
Q78: When looking at the critical path for
Q79: If it becomes necessary to delay one
Q80: While balancing assignments, a project manager must
Q81: Consider the following table of activities A
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents