If, during risk response development, you successfully identify how you will respond to a risk, contingency planning is unnecessary.
Correct Answer:
Verified
Q14: The first step in the risk management
Q15: Change management systems involve reporting, controlling, and
Q16: A risk profile is a list of
Q17: Fixed-price contracts are an example of transferring
Q18: One common mistake that is made early
Q20: Performance bonds, warranties, and guarantees are financial
Q21: One common mistake made early in the
Q22: _ focuses on how to respond to
Q23: Contingency funding is made up of contingency
Q24: Based on the following, which event should