When considering risk response development, assuming the risk because the chance of such an event is slim is known as _________ the risk.
A) transferring
B) mitigating
C) avoiding
D) retaining
E) escalating
Correct Answer:
Verified
Q67: Which of the following is the first
Q68: When considering risk response development, passing risk
Q69: The implications of an identified change need
Q70: The _ form identifies each risk event,
Q71: Choosing to move a concert indoors to
Q73: A list of questions that address traditional
Q74: When considering risk response development, changing the
Q75: Most changes on a project are related
Q76: When considering risk response development, reducing the
Q77: The _ matrix is divided into red,