Which of the following is NOT one of the basic rules to follow when developing project networks?
A) An activity cannot begin until all preceding activities have been completed.
B) Each activity must have a unique identification number.
C) Conditional statements are allowed but looping statements are not allowed.
D) An activity identification number must be larger than that of any preceding activities.
E) Networks flow from left to right.
Correct Answer:
Verified
Q19: Using free slack does not delay any
Q20: The forward pass through a project network
Q21: _ activities are to be completed immediately
Q22: On a project network, the activity times
Q23: Only activities that occur at the end
Q25: Arrows on an activity-on-node (AON) project network
Q26: A sequence of connected, dependent activities is
Q27: An activity that has more than one
Q28: The critical path in a project network
Q29: A project manager is building a project
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents