The bottom-up approach for estimating times and costs that uses costs from past projects that were similar to the current project is known as
A) detailed WBS work package estimates.
B) template method.
C) function point method.
D) time-phased cost estimates.
E) phase estimating.
Correct Answer:
Verified
Q49: When someone uses experience and / or
Q50: Refining estimates may be necessary for a
Q51: An external view of a Mega Project
Q52: The estimating factor that considers the decreasing
Q53: Large projects that have long time horizons
Q55: The estimating factor that considers the tendency
Q56: Refining Estimates may be necessary for a
Q57: Benefits of Reference Class Forecasting include
A) acts
Q58: The estimating factor that considers the skill
Q59: Companies are using which of the following
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents