Risk Assessment Derived from WBS and Technical Analyses and Customer

Question 94

Multiple Choice

Risk assessment derived from WBS and technical analyses and customer input is in place occurs in which of the following Maturity Model Levels?


A) Ad Hoc Project Management
B) Formal Application of Project Management
C) Institutionalization of Project Management
D) Management of Project Management System
E) Optimization of Project Management System

Correct Answer: