The ________ variance is the difference between the earned value to date and the baseline schedule.
A) schedule
B) cost
C) budget
D) time
E) performance
Correct Answer:
Verified
Q62: Causes for scope creep can include
A) newly
Q63: Because of their easy-to-understand visual format, _
Q64: The indicator that tells you the planned
Q65: The _ rule assumes credit is earned
Q66: When reviewing the cost variance on a
Q68: Baseline project budgets are derived from time-phasing
Q69: A project can have a negative schedule
Q70: A Cost / Schedule graph can be
Q71: Conditions or scope can change during execution,
Q72: A negative CV indicates the project is