Which of the following is not a benefit of Earned Value Management?
A) Measures accomplishments against plan and deliverables.
B) Provides a method for tracking directly to a problem work package and organization unit responsible.
C) Enables the project manager to ascertain problem paths within the project network and when the critical path is underperforming.
D) Alerts all stakeholders to early identification of problems and allows for quick, proactive corrective action.
E) Provides for accountability over individual portions of the overall budget for each organization unit.
Correct Answer:
Verified
Q87: Given that the AC = 500, PV
Q88: The _ index measures the project percent
Q89: A project manager learns that his project
Q90: Given an EAC of $10,000 and a
Q91: What is scope creep and how does
Q93: Two project complete indexes are used, depending
Q94: In reviewing the budget report of a
Q95: What is a "rubber baseline" and how
Q96: Conducting an earned value analysis requires three
Q97: Although it is very difficult to measure,
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents