When Engaging Stakeholders, a Project Manager Should

Question 32

Multiple Choice

When engaging stakeholders, a project manager should


A) develop a hands-on approach.
B) focus on the project team and their needs.
C) understand how different stakeholders can affect the project and manage that dependency.
D) manage and limit time negotiating with stakeholders outside of the organization.
E) refuse to be pulled by the demands of people who are not directly involved in the project.

Correct Answer: