Alice, a project manager, has undertaken a project to build an irrigation canal. Based on the resources allocated to her, she makes an initial estimate that the time required to dig the canal would be 20 days. She also prepares an alternative estimate by adding an additional resource that will allow the project to be completed in 10 days. This alternative estimate that Alice prepares is referred to as the _____.
A) crash duration
B) standard duration
C) slope duration
D) buffer duration
E) critical duration
Correct Answer:
Verified
Q36: Schedule slippage simply measures the amount by
Q37: A resource allocation decision may be intended
Q38: Pools of like resources from which labor
Q39: Activities that have duration but do not
Q40: In general, steady state demand for human
Q42: According to research, the best overall priority
Q43: Victoria, a project manager, has undertaken a
Q44: A project that must be completed within
Q45: Hamid, a project manager, has a workload
Q46: The primary cause of concern in resource
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents