Miros Inc., a recording studio, displays its recording process by using a network of nodes and arrows. The nodes are used to depict the activities involved in recording a song, such as setting up the instruments, and the arrows are used to depict the order of precedence of the activities. Which of the following project networks is Miros using in the given scenario?
A) A time-on-node network
B) An activity-on-arrow network
C) A time-on-arrow network
D) An activity-on-node network
E) An event-on-node network
Correct Answer:
Verified
Q62: High velocity is a goal of Agile
Q63: Paul, the marketing manager of a food
Q64: With scum, a prerequisite to being able
Q65: Consider a project network that begins with
Q66: Organ Bennett Inc., a public relations firm,
Q68: PERT was originally used for what type
Q69: Slack is calculated as?
A) LFT - EST
B)
Q70: Which of the following terms is most
Q71: An Agile team's velocity is only valid
Q72: The amount of time a noncritical task
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents