Ben is part of a new project in his company. He is asked to complete a task within two days, but he is only able to finish it in three days. Since the task assigned to him is noncritical in nature, the extra day taken by Ben does not cause a delay in the project. In this scenario, the additional day taken by Ben is known as _____.
A) flow time
B) throughput
C) slack
D) critical time
E) flowgrind
Correct Answer:
Verified
Q56: Technical dependencies are often harder to see
Q57: A start-to-finish linkage is the most common
Q58: Gantt charts are not adequate replacements for
Q59: Henry Gantt developed the Gantt chart.
Q60: The actual project duration will be known
Q62: High velocity is a goal of Agile
Q63: Paul, the marketing manager of a food
Q64: With scum, a prerequisite to being able
Q65: Consider a project network that begins with
Q66: Organ Bennett Inc., a public relations firm,
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents