According to the text, the use of sticky-notes can be particularly useful for constructing a(n)
A) RACI matrix
B) Work Breakdown Structure
C) Gantt chart
D) Design Structure Matrix
E) Aggregate Project Portfolio
Correct Answer:
Verified