Jeff Entered into a Building Contract with Mike Under Which

Question 38

True/False

Jeff entered into a building contract with Mike under which Jeff agreed to construct a garage on Mike's lot for $60,000. Lumber Supply Company supplied the lumber at Jeff's request, but when Jeff failed to pay for the material within a few weeks after it was supplied, the company filed a construction lien for $30,000 against Mike's property. If Mike ignores the lien claim, and pays the entire $60,000 to Jeff, Mike may be obliged to pay an amount equivalent to the sum he was required to hold back over again.

Correct Answer: