Slack refers to which of the following?
A) the latest time an activity can be finished without delaying the project
B) the amount of time an activity can be delayed without delaying the project
C) the earliest time an activity can be started without delaying the project
D) the latest time an activity can be started without delaying the project
Correct Answer:
Verified
Q51: Which of the following is not used
Q54: The project management process encompasses
A) planning.
B) scheduling.
C)
Q55: A project with a low but positive
Q55: A project consists of the following activities:
Q56: One disadvantage of a Gantt chart, especially
Q58: Smartsheet is a software package that supports
Q60: In project management, the slack in an
Q61: A project consists of the following four
Q64: A project consists of the following four
Q72: The slack time for an activity can
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents