As part of a time study a particular job was analyzed. The study included 20 job cycles and the following cumulative times and performance rating factors for each element were reported:
Assuming an allowance factor of 20% the standard time for this job would be
A) 10.08 minutes.
B) 12.10 minutes.
C) 14.73 minutes.
D) 16.58 minutes.
Correct Answer:
Verified
Q4: Scientific management divides jobs into their most
Q7: Empowerment involves giving employees the authority and
Q12: Job rotation often requires cross-training of employees.
Q16: With total quality management,employees receive broad job
Q20: With total quality management,employees are usually given
Q22: A work sampling study is being conducted
Q24: How many observations should be taken to
Q26: How many cycles should be used in
Q37: Work measurement and time study were introduced
Q39: Explain the history and principles of scientific
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents