A company has accepted a contract to produce a special electric motor. The number of direct labour hours required to produce the first motor is 250. If an 85% learning curve applies to the production of motors, then the number of labour hours needed to produce the 4th motor is
A) 212.5 hours.
B) 180.6 hours.
C) 153.5 hours.
D) 0 37.5 hours
Correct Answer:
Verified
Q44: In a piece-rate wage system a worker's
Q52: _ involves the horizontal movement or a
Q61: A graph that illustrates the improvement rate
Q63: The amount of time a worker and
Q64: Which of the following would most likely
Q72: The gradual shift from treating employees as
Q80: _ illustrate the improvement rate of workers
Q104: Worker-machine chart determines
A) if capital for workers
Q105: The direct labour times required to produce
Q110: A learning curve illustrates that increasing the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents