A Cost Report Showing Budget Overruns on a Project Completed

Question 37

Multiple Choice

A cost report showing budget overruns on a project completed during the prior month is an example of which type of control?


A) Preliminary control
B) Cost control
C) Managerial control
D) Steering control
E) Feedback control